Zerra DC proposes a four-building AI campus in Queensland

Zerra DC wants to build up to four AI-ready data-center buildings of 36,000 square meters each on a 725.5-hectare site in regional Queensland, and has filed the four-phase proposal with the Western Downs Regional Council. The first phase would include a 540MVA substation and battery-backed power conditioning. The company says the campus would use air cooling rather than evaporative water cooling, which draws heavily on local water.

Waiting onCouncil approval and construction - the proposal sits with the Western Downs Regional Council and no work has started on the site.