PJM would curtail large new data centers first during shortages
PJM has proposed placing new single-site loads of 50MW or more that arrive without their own new power supply on interim service. In a local shortage, those customers would be first in line for curtailment and would be compensated less than others for cutting their demand. An AI campus shopping for grid power in PJM territory would be left with three routes: build new supply, accept interruption, or wait for firm service.
Waiting onEffective date - PJM has proposed applying the large-load rules to qualifying new service from June 1, 2027.