Magnora locks in a 2029 grid connection for a Finnish campus

Magnora secured a firm grid connection for its Hämeenlinna data-center project near Helsinki, developed with Northern Europe Energy Group. The 150,000-square-meter project had been described as 120MW, and Magnora now says the potential capacity is higher without putting a revised figure on it. Electricity access is what decides which European campuses get built, and Magnora says this connection is scheduled for the first quarter of 2029, with a possible move up to the second half of 2028.

Waiting onGrid connection and construction - Magnora holds a firm connection agreement and the campus has not been built.