TVA raises power charges for data centers seeking connections

Image: datacenterdynamics.com

TVA pulled data centers out of its manufacturing service customer class, a reclassification expected to lift their power charges by about 10%. New developments will also pay capacity-commitment charges of roughly $1.5 million per megawatt, spread over three to five years. Anyone planning a large compute project in TVA territory now has a price attached to the grid capacity they are asking for, and more of the bill for new generation and grid work lands on the developer.