Pennsylvania ties fast data-center permits to bringing new power
Pennsylvania called for rules covering data centers above 25MW that want preferential permitting: secure incremental power capacity, or be curtailed ahead of other customers when the grid is under emergency strain. The same order asks that those data centers carry the relevant emergency-auction and grid-upgrade costs. Households and other businesses would then absorb less of the expansion bill, and the state's approach lines up with the curtailment framework PJM has proposed.