Applied Digital makes first Polaris Forge 2 hall service-ready

Yesterday, Applied Digital said its first 25MW hall at Polaris Forge 2 in North Dakota was ready for service. It has also completed base-build commissioning (testing the facility's basic systems) for the first 75MW. The remaining 50MW of that portion still needs to be fitted out and delivered to customers.