Microsoft withdraws from Essex data-center project after power delays

Image: datacenterdynamics.com

Microsoft withdrew from Nscale's Loughton project in Essex, where it had planned a UK supercomputer as the site's main tenant. Nscale originally described 50 megawatts of AI and high-performance computing capacity, with completion targeted for late 2026, but national-grid power is expected only in the 2030s. Nscale says it remains committed to Loughton and is exploring alternative power supplies and other UK expansion sites.