Oracle seeks 2GW of renewable power for unfinished AI campus
Oracle sought proposals on Sept. 8 for 2GW of new renewable-energy projects in New Mexico as it builds Project Jupiter, its data center for OpenAI. The company also pledged $1 million for carbon-capture research tied to the project, which is 26% complete. Project Jupiter’s planned 2.45GW fuel-cell supply will initially run on natural gas. The proposed renewable projects are intended to match the facility’s energy use and would not directly supply it.
Waiting onCompletion and permitting - Project Jupiter is 26% complete, and its air-quality permitting process is paused.