Kentucky approves 482MW power deal for TeraWulf campus
Kentucky regulators approved a 482MW electrical service agreement for TeraWulf's planned Justified Data Campus in Hancock County. The deal runs through an existing grid connection and makes TeraWulf responsible for the costs tied to its own load and to customer-specific infrastructure. Electricity, not land or chips, is usually what holds up a new AI computing site, and this one now has a defined route to a large connection already in the ground.